Accessibility to Inclusive Education Project - Part II (The construction of the Southern Wing):
Project Objective:
To complete the additional floor on the southern side in order to include facilities that will enhance the accessibility of the Inclusive educational setting.
Project Outcome:
In addition to more classrooms, a Science Laboratory and an multi-functional hall was added on the southern wing.
Project Duration:
The construction work was completed in Summer 2006.
Project Partners:
Recipient of Grant: The Jerusalem Princess Basma Centre for Disabled Children.
Grantor: Bait Mal Al-Qods Al-Sharif - Morocco
Project Implementation: Local Office of Bait Mal al-Qods Al-Sahrif - Ramallah
Project Cost:
USD 300,000 |